Overall Summary

Total Spent Amount (PGK)
15 Billions
15.6% of the Budget
Overall Completion
3%
-2.4% Deviation
Time Exceeded Contracts
4
5% of all contracts
Contracts with Varied Value
41
+5 in the last month
Contracts in Defects Liability Period
56
+6 in the last month
Contracts experiencing late payment
35
+7 in the last month
Contracts given extension of time
46
+2 in the last month
Value of Contract Variation (PGK)
133 Millions
0.9% of the Budget
Payable Amount (PGK)
5 Billions
3.6% of the Budget
Budget Balance (PGK)
10 Billions
84.6% of the Budget
Contractors
Name

Covec PNG Ltd

Value

229.99M

Completion %

12%

Name

Dekenai Constructions Ltd

Value

196.40M

Completion %

14%

Name

Aunge Punks Engineering Ltd

Value

184.35M

Completion %

9%

Name

Kobul Constructor

Value

157.23M

Completion %

13%

Name

TED Construction Ltd

Value

148.62M

Completion %

25%

Name

JV PNG Investment Construction Ltd

Value

135.99M

Completion %

18%

Overall Progress
Corridor-wise Progress
Under-delivered Contractors
# Contractor Name No. of Projects Exp Com % Act Com %
Tupet Enterprises Ltd 44 34% 6%
Shrim Construction 56 46% 15%
Palmdust Transport 28 54% 12%
Fabers Civ Works 19 50% 11%
Contract Budget Completion % Paid Amount Expected End Date
CSTB 2930 466M 31% 51M 2024-05-16
CW-14-2016 853M 15% 97M 2024-05-16
50-NBD/DoW-20/01 to 20/06 289M 15% 42M 2024-05-16
DoW AROB SK04/2020 272M 25% 63M 2024-05-16
CW-13-2022 222M 12% 94M 2024-05-16
NBE - INF/PIP - 2021 - 01 585M 31% 26M 2024-05-16
WNBPSTB/DOW-CE:01/2018 724M 28% 103M 2024-05-16
PSTBWNB/DOW-CE:03/2018 196M 23% 101M 2024-05-16
PSTB-COI-WNBP-02/2018 716M 11% 26M 2024-05-16
SC44-PGoWNB - 2019 763M 38% 62M 2024-05-16
MC/COI-KHR/WNBP-01/2020 705M 18% 116M 2024-05-16