Total Spent Amount (PGK)
12 Billions
15.6% of the Budget
Overall Completion
5%
-2.4% Deviation
Time Exceeded Contracts
4
5% of all contracts
Contracts with Varied Value
68
+5 in the last month
Contracts in Defects Liability Period
13
+6 in the last month
Contracts experiencing late payment
49
+7 in the last month
Contracts given extension of time
40
+2 in the last month
Value of Contract Variation (PGK)
245 Millions
0.9% of the Budget
Payable Amount (PGK)
2 Billions
3.6% of the Budget
Budget Balance (PGK)
18 Billions
84.6% of the Budget
Contractors
![]()
Name
Covec PNG Ltd |
Value
229.99M |
Completion %
12% |
![]()
Name
Dekenai Constructions Ltd |
Value
196.40M |
Completion %
14% |
![]()
Name
Aunge Punks Engineering Ltd |
Value
184.35M |
Completion %
9% |
![]()
Name
Kobul Constructor |
Value
157.23M |
Completion %
13% |
![]()
Name
TED Construction Ltd |
Value
148.62M |
Completion %
25% |
![]()
Name
JV PNG Investment Construction Ltd |
Value
135.99M |
Completion %
18% |
Contracts Overview
Contract | Budget | Completion % | Paid Amount | Expected End Date |
---|---|---|---|---|
CSTB 2930 | 366M | 28% | 26M | 2024-05-16 |
CW-14-2016 | 899M | 33% | 24M | 2024-05-16 |
50-NBD/DoW-20/01 to 20/06 | 787M | 30% | 88M | 2024-05-16 |
DoW AROB SK04/2020 | 389M | 39% | 93M | 2024-05-16 |
CW-13-2022 | 831M | 38% | 41M | 2024-05-16 |
NBE - INF/PIP - 2021 - 01 | 117M | 23% | 86M | 2024-05-16 |
WNBPSTB/DOW-CE:01/2018 | 515M | 34% | 83M | 2024-05-16 |
PSTBWNB/DOW-CE:03/2018 | 286M | 22% | 88M | 2024-05-16 |
PSTB-COI-WNBP-02/2018 | 896M | 21% | 105M | 2024-05-16 |
SC44-PGoWNB - 2019 | 790M | 16% | 79M | 2024-05-16 |
MC/COI-KHR/WNBP-01/2020 | 817M | 36% | 71M | 2024-05-16 |