Region Analytics

Total Spent Amount (PGK)
13 Billions
15.6% of the Budget
Overall Completion
4%
-2.4% Deviation
Time Exceeded Contracts
4
5% of all contracts
Contracts with Varied Value
27
+5 in the last month
Contracts in Defects Liability Period
24
+6 in the last month
Contracts experiencing late payment
46
+7 in the last month
Contracts given extension of time
17
+2 in the last month
Value of Contract Variation (PGK)
92 Millions
0.9% of the Budget
Payable Amount (PGK)
1 Billions
3.6% of the Budget
Budget Balance (PGK)
15 Billions
84.6% of the Budget
Contractors
Name

Covec PNG Ltd

Value

229.99M

Completion %

12%

Name

Dekenai Constructions Ltd

Value

196.40M

Completion %

14%

Name

Aunge Punks Engineering Ltd

Value

184.35M

Completion %

9%

Name

Kobul Constructor

Value

157.23M

Completion %

13%

Name

TED Construction Ltd

Value

148.62M

Completion %

25%

Name

JV PNG Investment Construction Ltd

Value

135.99M

Completion %

18%

Overall Progress
Corridor-wise Progress
Under-delivered Contractors
# Contractor Name No. of Projects Exp Com % Act Com %
Tupet Enterprises Ltd 44 34% 6%
Shrim Construction 56 46% 15%
Palmdust Transport 28 54% 12%
Fabers Civ Works 19 50% 11%
Contract Budget Completion % Paid Amount Expected End Date
CSTB 2930 833M 12% 103M 2024-05-16
CW-14-2016 351M 17% 105M 2024-05-16
50-NBD/DoW-20/01 to 20/06 311M 35% 45M 2024-05-16
DoW AROB SK04/2020 589M 17% 110M 2024-05-16
CW-13-2022 169M 38% 30M 2024-05-16
NBE - INF/PIP - 2021 - 01 150M 26% 96M 2024-05-16
WNBPSTB/DOW-CE:01/2018 653M 25% 27M 2024-05-16
PSTBWNB/DOW-CE:03/2018 377M 33% 30M 2024-05-16
PSTB-COI-WNBP-02/2018 456M 16% 73M 2024-05-16
SC44-PGoWNB - 2019 606M 18% 28M 2024-05-16
MC/COI-KHR/WNBP-01/2020 135M 22% 38M 2024-05-16