Region Analytics

Total Spent Amount (PGK)
10 Billions
15.6% of the Budget
Overall Completion
4%
-2.4% Deviation
Time Exceeded Contracts
4
5% of all contracts
Contracts with Varied Value
44
+5 in the last month
Contracts in Defects Liability Period
47
+6 in the last month
Contracts experiencing late payment
54
+7 in the last month
Contracts given extension of time
33
+2 in the last month
Value of Contract Variation (PGK)
257 Millions
0.9% of the Budget
Payable Amount (PGK)
4 Billions
3.6% of the Budget
Budget Balance (PGK)
15 Billions
84.6% of the Budget
Contractors
Name

Covec PNG Ltd

Value

229.99M

Completion %

12%

Name

Dekenai Constructions Ltd

Value

196.40M

Completion %

14%

Name

Aunge Punks Engineering Ltd

Value

184.35M

Completion %

9%

Name

Kobul Constructor

Value

157.23M

Completion %

13%

Name

TED Construction Ltd

Value

148.62M

Completion %

25%

Name

JV PNG Investment Construction Ltd

Value

135.99M

Completion %

18%

Overall Progress
Corridor-wise Progress
Under-delivered Contractors
# Contractor Name No. of Projects Exp Com % Act Com %
Tupet Enterprises Ltd 44 34% 6%
Shrim Construction 56 46% 15%
Palmdust Transport 28 54% 12%
Fabers Civ Works 19 50% 11%
Contract Budget Completion % Paid Amount Expected End Date
CSTB 2930 428M 39% 76M 2024-05-16
CW-14-2016 166M 20% 42M 2024-05-16
50-NBD/DoW-20/01 to 20/06 641M 11% 34M 2024-05-16
DoW AROB SK04/2020 490M 29% 87M 2024-05-16
CW-13-2022 628M 26% 63M 2024-05-16
NBE - INF/PIP - 2021 - 01 283M 40% 99M 2024-05-16
WNBPSTB/DOW-CE:01/2018 530M 40% 41M 2024-05-16
PSTBWNB/DOW-CE:03/2018 146M 19% 119M 2024-05-16
PSTB-COI-WNBP-02/2018 735M 14% 42M 2024-05-16
SC44-PGoWNB - 2019 354M 15% 75M 2024-05-16
MC/COI-KHR/WNBP-01/2020 818M 24% 30M 2024-05-16