Corridor Analytics

Total Spent Amount (PGK)
6 Billions
15.6% of the Budget
Overall Completion
9%
-2.4% Deviation
Time Exceeded Contracts
4
5% of all contracts
Contracts with Varied Value
75
+5 in the last month
Contracts in Defects Liability Period
34
+6 in the last month
Contracts experiencing late payment
14
+7 in the last month
Contracts given extension of time
57
+2 in the last month
Value of Contract Variation (PGK)
89 Millions
0.9% of the Budget
Payable Amount (PGK)
2 Billions
3.6% of the Budget
Budget Balance (PGK)
6 Billions
84.6% of the Budget
Contractors
Name

Covec PNG Ltd

Value

229.99M

Completion %

12%

Name

Dekenai Constructions Ltd

Value

196.40M

Completion %

14%

Name

Aunge Punks Engineering Ltd

Value

184.35M

Completion %

9%

Name

Kobul Constructor

Value

157.23M

Completion %

13%

Name

TED Construction Ltd

Value

148.62M

Completion %

25%

Name

JV PNG Investment Construction Ltd

Value

135.99M

Completion %

18%

Overall Progress
Under-delivered Contractors
# Contractor Name No. of Projects Exp Com % Act Com %
Tupet Enterprises Ltd 44 34% 6%
Shrim Construction 56 46% 15%
Palmdust Transport 28 54% 12%
Fabers Civ Works 19 50% 11%
Contract Budget Completion % Paid Amount Expected End Date
CSTB 2930 447M 25% 85M 2024-05-16
CW-14-2016 327M 17% 110M 2024-05-16
50-NBD/DoW-20/01 to 20/06 889M 12% 114M 2024-05-16
DoW AROB SK04/2020 854M 21% 23M 2024-05-16
CW-13-2022 91M 21% 116M 2024-05-16
NBE - INF/PIP - 2021 - 01 247M 23% 31M 2024-05-16
WNBPSTB/DOW-CE:01/2018 619M 22% 110M 2024-05-16
PSTBWNB/DOW-CE:03/2018 575M 33% 64M 2024-05-16
PSTB-COI-WNBP-02/2018 396M 39% 43M 2024-05-16
SC44-PGoWNB - 2019 89M 10% 30M 2024-05-16
MC/COI-KHR/WNBP-01/2020 381M 20% 90M 2024-05-16