Corridor Analytics

Total Spent Amount (PGK)
9 Billions
15.6% of the Budget
Overall Completion
3%
-2.4% Deviation
Time Exceeded Contracts
4
5% of all contracts
Contracts with Varied Value
86
+5 in the last month
Contracts in Defects Liability Period
36
+6 in the last month
Contracts experiencing late payment
36
+7 in the last month
Contracts given extension of time
22
+2 in the last month
Value of Contract Variation (PGK)
257 Millions
0.9% of the Budget
Payable Amount (PGK)
3 Billions
3.6% of the Budget
Budget Balance (PGK)
11 Billions
84.6% of the Budget
Contractors
Name

Covec PNG Ltd

Value

229.99M

Completion %

12%

Name

Dekenai Constructions Ltd

Value

196.40M

Completion %

14%

Name

Aunge Punks Engineering Ltd

Value

184.35M

Completion %

9%

Name

Kobul Constructor

Value

157.23M

Completion %

13%

Name

TED Construction Ltd

Value

148.62M

Completion %

25%

Name

JV PNG Investment Construction Ltd

Value

135.99M

Completion %

18%

Overall Progress
Under-delivered Contractors
# Contractor Name No. of Projects Exp Com % Act Com %
Tupet Enterprises Ltd 44 34% 6%
Shrim Construction 56 46% 15%
Palmdust Transport 28 54% 12%
Fabers Civ Works 19 50% 11%
Contract Budget Completion % Paid Amount Expected End Date
CSTB 2930 527M 10% 45M 2024-05-16
CW-14-2016 374M 18% 32M 2024-05-16
50-NBD/DoW-20/01 to 20/06 342M 13% 78M 2024-05-16
DoW AROB SK04/2020 442M 25% 37M 2024-05-16
CW-13-2022 173M 39% 24M 2024-05-16
NBE - INF/PIP - 2021 - 01 400M 22% 95M 2024-05-16
WNBPSTB/DOW-CE:01/2018 819M 26% 36M 2024-05-16
PSTBWNB/DOW-CE:03/2018 188M 29% 68M 2024-05-16
PSTB-COI-WNBP-02/2018 365M 27% 37M 2024-05-16
SC44-PGoWNB - 2019 484M 38% 97M 2024-05-16
MC/COI-KHR/WNBP-01/2020 565M 17% 90M 2024-05-16