Total Spent Amount (PGK)
12 Billions
15.6% of the Budget
Overall Completion
8%
-2.4% Deviation
Time Exceeded Contracts
5
5% of all contracts
Contracts with Varied Value
49
+5 in the last month
Contracts in Defects Liability Period
34
+6 in the last month
Contracts experiencing late payment
28
+7 in the last month
Contracts given extension of time
17
+2 in the last month
Value of Contract Variation (PGK)
226 Millions
0.9% of the Budget
Payable Amount (PGK)
2 Billions
3.6% of the Budget
Budget Balance (PGK)
17 Billions
84.6% of the Budget
Contractors
![]()
Name
Covec PNG Ltd |
Value
229.99M |
Completion %
12% |
![]()
Name
Dekenai Constructions Ltd |
Value
196.40M |
Completion %
14% |
![]()
Name
Aunge Punks Engineering Ltd |
Value
184.35M |
Completion %
9% |
![]()
Name
Kobul Constructor |
Value
157.23M |
Completion %
13% |
![]()
Name
TED Construction Ltd |
Value
148.62M |
Completion %
25% |
![]()
Name
JV PNG Investment Construction Ltd |
Value
135.99M |
Completion %
18% |
Contracts Overview
Contract | Budget | Completion % | Paid Amount | Expected End Date |
---|---|---|---|---|
CSTB 2930 | 690M | 38% | 46M | 2024-05-16 |
CW-14-2016 | 598M | 28% | 35M | 2024-05-16 |
50-NBD/DoW-20/01 to 20/06 | 588M | 12% | 84M | 2024-05-16 |
DoW AROB SK04/2020 | 544M | 26% | 82M | 2024-05-16 |
CW-13-2022 | 867M | 10% | 46M | 2024-05-16 |
NBE - INF/PIP - 2021 - 01 | 472M | 16% | 26M | 2024-05-16 |
WNBPSTB/DOW-CE:01/2018 | 649M | 18% | 32M | 2024-05-16 |
PSTBWNB/DOW-CE:03/2018 | 872M | 30% | 102M | 2024-05-16 |
PSTB-COI-WNBP-02/2018 | 133M | 31% | 101M | 2024-05-16 |
SC44-PGoWNB - 2019 | 273M | 39% | 64M | 2024-05-16 |
MC/COI-KHR/WNBP-01/2020 | 838M | 12% | 99M | 2024-05-16 |