Total Spent Amount (PGK)
6 Billions
15.6% of the Budget
Overall Completion
7%
-2.4% Deviation
Time Exceeded Contracts
5
5% of all contracts
Contracts with Varied Value
53
+5 in the last month
Contracts in Defects Liability Period
33
+6 in the last month
Contracts experiencing late payment
55
+7 in the last month
Contracts given extension of time
33
+2 in the last month
Value of Contract Variation (PGK)
148 Millions
0.9% of the Budget
Payable Amount (PGK)
1 Billions
3.6% of the Budget
Budget Balance (PGK)
14 Billions
84.6% of the Budget
Contractors
![]()
Name
Covec PNG Ltd |
Value
229.99M |
Completion %
12% |
![]()
Name
Dekenai Constructions Ltd |
Value
196.40M |
Completion %
14% |
![]()
Name
Aunge Punks Engineering Ltd |
Value
184.35M |
Completion %
9% |
![]()
Name
Kobul Constructor |
Value
157.23M |
Completion %
13% |
![]()
Name
TED Construction Ltd |
Value
148.62M |
Completion %
25% |
![]()
Name
JV PNG Investment Construction Ltd |
Value
135.99M |
Completion %
18% |
Contracts Overview
Contract | Budget | Completion % | Paid Amount | Expected End Date |
---|---|---|---|---|
CSTB 2930 | 324M | 15% | 116M | 2024-05-16 |
CW-14-2016 | 261M | 32% | 106M | 2024-05-16 |
50-NBD/DoW-20/01 to 20/06 | 502M | 27% | 62M | 2024-05-16 |
DoW AROB SK04/2020 | 743M | 10% | 110M | 2024-05-16 |
CW-13-2022 | 829M | 17% | 79M | 2024-05-16 |
NBE - INF/PIP - 2021 - 01 | 481M | 22% | 92M | 2024-05-16 |
WNBPSTB/DOW-CE:01/2018 | 541M | 23% | 110M | 2024-05-16 |
PSTBWNB/DOW-CE:03/2018 | 381M | 11% | 35M | 2024-05-16 |
PSTB-COI-WNBP-02/2018 | 805M | 22% | 79M | 2024-05-16 |
SC44-PGoWNB - 2019 | 403M | 31% | 83M | 2024-05-16 |
MC/COI-KHR/WNBP-01/2020 | 870M | 12% | 48M | 2024-05-16 |