Total Spent Amount (PGK)
8 Billions
15.6% of the Budget
Overall Completion
7%
-2.4% Deviation
Time Exceeded Contracts
4
5% of all contracts
Contracts with Varied Value
72
+5 in the last month
Contracts in Defects Liability Period
19
+6 in the last month
Contracts experiencing late payment
29
+7 in the last month
Contracts given extension of time
51
+2 in the last month
Value of Contract Variation (PGK)
179 Millions
0.9% of the Budget
Payable Amount (PGK)
1 Billions
3.6% of the Budget
Budget Balance (PGK)
13 Billions
84.6% of the Budget
Contractors
![]()
Name
Covec PNG Ltd |
Value
229.99M |
Completion %
12% |
![]()
Name
Dekenai Constructions Ltd |
Value
196.40M |
Completion %
14% |
![]()
Name
Aunge Punks Engineering Ltd |
Value
184.35M |
Completion %
9% |
![]()
Name
Kobul Constructor |
Value
157.23M |
Completion %
13% |
![]()
Name
TED Construction Ltd |
Value
148.62M |
Completion %
25% |
![]()
Name
JV PNG Investment Construction Ltd |
Value
135.99M |
Completion %
18% |
Contracts Overview
Contract | Budget | Completion % | Paid Amount | Expected End Date |
---|---|---|---|---|
CSTB 2930 | 409M | 34% | 35M | 2024-05-16 |
CW-14-2016 | 247M | 22% | 55M | 2024-05-16 |
50-NBD/DoW-20/01 to 20/06 | 494M | 14% | 106M | 2024-05-16 |
DoW AROB SK04/2020 | 529M | 12% | 103M | 2024-05-16 |
CW-13-2022 | 124M | 21% | 53M | 2024-05-16 |
NBE - INF/PIP - 2021 - 01 | 691M | 35% | 37M | 2024-05-16 |
WNBPSTB/DOW-CE:01/2018 | 485M | 36% | 70M | 2024-05-16 |
PSTBWNB/DOW-CE:03/2018 | 435M | 15% | 100M | 2024-05-16 |
PSTB-COI-WNBP-02/2018 | 856M | 21% | 97M | 2024-05-16 |
SC44-PGoWNB - 2019 | 542M | 40% | 98M | 2024-05-16 |
MC/COI-KHR/WNBP-01/2020 | 132M | 29% | 108M | 2024-05-16 |