Contractor Analytics

Total Contract Amount (PGK)
12 Billions
15.6% of the Budget
Overall Completion
9%
-2.4% Deviation
Time Exceeded Contracts
5
5% of all contracts
Contracts with Varied Value
57
+5 in the last month
Contracts in Defects Liability Period
46
+6 in the last month
Contracts experiencing late payment
42
+7 in the last month
Contracts given extension of time
32
+2 in the last month
Value of Contract Variation (PGK)
225 Millions
0.9% of the Budget
Payable Amount (PGK)
3 Billions
3.6% of the Budget
Budget Balance (PSK)
16 Billions
84.6% of the Budget
Overall Progress
Corridor-wise Progress
Contract Budget Completion % Paid Amount Expected End Date
CSTB 2930 680M 31% 120M 2024-05-16
CW-14-2016 394M 27% 30M 2024-05-16
50-NBD/DoW-20/01 to 20/06 831M 26% 31M 2024-05-16
DoW AROB SK04/2020 683M 24% 62M 2024-05-16
CW-13-2022 677M 29% 37M 2024-05-16
NBE - INF/PIP - 2021 - 01 632M 15% 64M 2024-05-16
WNBPSTB/DOW-CE:01/2018 351M 30% 69M 2024-05-16
PSTBWNB/DOW-CE:03/2018 732M 35% 46M 2024-05-16
PSTB-COI-WNBP-02/2018 407M 35% 61M 2024-05-16
SC44-PGoWNB - 2019 283M 30% 60M 2024-05-16
MC/COI-KHR/WNBP-01/2020 303M 25% 100M 2024-05-16