Contractor Analytics

Total Contract Amount (PGK)
6 Billions
15.6% of the Budget
Overall Completion
13%
-2.4% Deviation
Time Exceeded Contracts
5
5% of all contracts
Contracts with Varied Value
94
+5 in the last month
Contracts in Defects Liability Period
25
+6 in the last month
Contracts experiencing late payment
36
+7 in the last month
Contracts given extension of time
18
+2 in the last month
Value of Contract Variation (PGK)
142 Millions
0.9% of the Budget
Payable Amount (PGK)
1 Billions
3.6% of the Budget
Budget Balance (PSK)
10 Billions
84.6% of the Budget
Overall Progress
Corridor-wise Progress
Contract Budget Completion % Paid Amount Expected End Date
CSTB 2930 208M 24% 24M 2024-05-16
CW-14-2016 717M 32% 49M 2024-05-16
50-NBD/DoW-20/01 to 20/06 308M 30% 82M 2024-05-16
DoW AROB SK04/2020 180M 25% 76M 2024-05-16
CW-13-2022 257M 18% 109M 2024-05-16
NBE - INF/PIP - 2021 - 01 571M 20% 55M 2024-05-16
WNBPSTB/DOW-CE:01/2018 659M 36% 111M 2024-05-16
PSTBWNB/DOW-CE:03/2018 762M 27% 93M 2024-05-16
PSTB-COI-WNBP-02/2018 734M 34% 49M 2024-05-16
SC44-PGoWNB - 2019 311M 38% 60M 2024-05-16
MC/COI-KHR/WNBP-01/2020 791M 15% 96M 2024-05-16