Contractor Analytics

Total Contract Amount (PGK)
14 Billions
15.6% of the Budget
Overall Completion
11%
-2.4% Deviation
Time Exceeded Contracts
4
5% of all contracts
Contracts with Varied Value
52
+5 in the last month
Contracts in Defects Liability Period
37
+6 in the last month
Contracts experiencing late payment
33
+7 in the last month
Contracts given extension of time
44
+2 in the last month
Value of Contract Variation (PGK)
87 Millions
0.9% of the Budget
Payable Amount (PGK)
4 Billions
3.6% of the Budget
Budget Balance (PSK)
16 Billions
84.6% of the Budget
Overall Progress
Corridor-wise Progress
Contract Budget Completion % Paid Amount Expected End Date
CSTB 2930 561M 26% 120M 2024-05-16
CW-14-2016 819M 11% 64M 2024-05-16
50-NBD/DoW-20/01 to 20/06 658M 35% 108M 2024-05-16
DoW AROB SK04/2020 288M 12% 119M 2024-05-16
CW-13-2022 796M 18% 109M 2024-05-16
NBE - INF/PIP - 2021 - 01 695M 35% 94M 2024-05-16
WNBPSTB/DOW-CE:01/2018 788M 10% 20M 2024-05-16
PSTBWNB/DOW-CE:03/2018 239M 24% 76M 2024-05-16
PSTB-COI-WNBP-02/2018 437M 29% 102M 2024-05-16
SC44-PGoWNB - 2019 348M 30% 65M 2024-05-16
MC/COI-KHR/WNBP-01/2020 734M 34% 93M 2024-05-16