Contractor Analytics

Total Contract Amount (PGK)
14 Billions
15.6% of the Budget
Overall Completion
5%
-2.4% Deviation
Time Exceeded Contracts
5
5% of all contracts
Contracts with Varied Value
77
+5 in the last month
Contracts in Defects Liability Period
50
+6 in the last month
Contracts experiencing late payment
39
+7 in the last month
Contracts given extension of time
15
+2 in the last month
Value of Contract Variation (PGK)
81 Millions
0.9% of the Budget
Payable Amount (PGK)
5 Billions
3.6% of the Budget
Budget Balance (PSK)
18 Billions
84.6% of the Budget
Overall Progress
Corridor-wise Progress
Contract Budget Completion % Paid Amount Expected End Date
CSTB 2930 308M 39% 116M 2024-05-16
CW-14-2016 226M 37% 110M 2024-05-16
50-NBD/DoW-20/01 to 20/06 153M 10% 35M 2024-05-16
DoW AROB SK04/2020 268M 27% 109M 2024-05-16
CW-13-2022 627M 37% 39M 2024-05-16
NBE - INF/PIP - 2021 - 01 89M 21% 71M 2024-05-16
WNBPSTB/DOW-CE:01/2018 602M 17% 36M 2024-05-16
PSTBWNB/DOW-CE:03/2018 163M 33% 78M 2024-05-16
PSTB-COI-WNBP-02/2018 418M 14% 63M 2024-05-16
SC44-PGoWNB - 2019 866M 36% 64M 2024-05-16
MC/COI-KHR/WNBP-01/2020 785M 25% 93M 2024-05-16