Contractor Analytics

Total Contract Amount (PGK)
14 Billions
15.6% of the Budget
Overall Completion
12%
-2.4% Deviation
Time Exceeded Contracts
4
5% of all contracts
Contracts with Varied Value
36
+5 in the last month
Contracts in Defects Liability Period
36
+6 in the last month
Contracts experiencing late payment
11
+7 in the last month
Contracts given extension of time
34
+2 in the last month
Value of Contract Variation (PGK)
83 Millions
0.9% of the Budget
Payable Amount (PGK)
3 Billions
3.6% of the Budget
Budget Balance (PSK)
7 Billions
84.6% of the Budget
Overall Progress
Corridor-wise Progress
Contract Budget Completion % Paid Amount Expected End Date
CSTB 2930 469M 39% 100M 2024-05-16
CW-14-2016 786M 21% 64M 2024-05-16
50-NBD/DoW-20/01 to 20/06 244M 11% 73M 2024-05-16
DoW AROB SK04/2020 321M 35% 48M 2024-05-16
CW-13-2022 604M 16% 94M 2024-05-16
NBE - INF/PIP - 2021 - 01 560M 31% 58M 2024-05-16
WNBPSTB/DOW-CE:01/2018 664M 15% 118M 2024-05-16
PSTBWNB/DOW-CE:03/2018 653M 19% 80M 2024-05-16
PSTB-COI-WNBP-02/2018 111M 13% 24M 2024-05-16
SC44-PGoWNB - 2019 820M 25% 85M 2024-05-16
MC/COI-KHR/WNBP-01/2020 890M 21% 98M 2024-05-16