Contractor Analytics

Total Contract Amount (PGK)
5 Billions
15.6% of the Budget
Overall Completion
6%
-2.4% Deviation
Time Exceeded Contracts
5
5% of all contracts
Contracts with Varied Value
76
+5 in the last month
Contracts in Defects Liability Period
25
+6 in the last month
Contracts experiencing late payment
11
+7 in the last month
Contracts given extension of time
50
+2 in the last month
Value of Contract Variation (PGK)
256 Millions
0.9% of the Budget
Payable Amount (PGK)
5 Billions
3.6% of the Budget
Budget Balance (PSK)
6 Billions
84.6% of the Budget
Overall Progress
Corridor-wise Progress
Contract Budget Completion % Paid Amount Expected End Date
CSTB 2930 763M 35% 78M 2024-05-16
CW-14-2016 630M 22% 95M 2024-05-16
50-NBD/DoW-20/01 to 20/06 262M 16% 28M 2024-05-16
DoW AROB SK04/2020 828M 14% 20M 2024-05-16
CW-13-2022 616M 17% 26M 2024-05-16
NBE - INF/PIP - 2021 - 01 299M 33% 81M 2024-05-16
WNBPSTB/DOW-CE:01/2018 659M 35% 61M 2024-05-16
PSTBWNB/DOW-CE:03/2018 847M 30% 93M 2024-05-16
PSTB-COI-WNBP-02/2018 838M 40% 78M 2024-05-16
SC44-PGoWNB - 2019 653M 35% 59M 2024-05-16
MC/COI-KHR/WNBP-01/2020 470M 16% 57M 2024-05-16