Contractor Analytics

Total Contract Amount (PGK)
4 Billions
15.6% of the Budget
Overall Completion
7%
-2.4% Deviation
Time Exceeded Contracts
4
5% of all contracts
Contracts with Varied Value
43
+5 in the last month
Contracts in Defects Liability Period
38
+6 in the last month
Contracts experiencing late payment
56
+7 in the last month
Contracts given extension of time
38
+2 in the last month
Value of Contract Variation (PGK)
193 Millions
0.9% of the Budget
Payable Amount (PGK)
1 Billions
3.6% of the Budget
Budget Balance (PSK)
18 Billions
84.6% of the Budget
Overall Progress
Corridor-wise Progress
Contract Budget Completion % Paid Amount Expected End Date
CSTB 2930 295M 21% 26M 2024-05-16
CW-14-2016 328M 27% 49M 2024-05-16
50-NBD/DoW-20/01 to 20/06 271M 17% 23M 2024-05-16
DoW AROB SK04/2020 294M 18% 40M 2024-05-16
CW-13-2022 698M 17% 116M 2024-05-16
NBE - INF/PIP - 2021 - 01 824M 28% 95M 2024-05-16
WNBPSTB/DOW-CE:01/2018 761M 13% 96M 2024-05-16
PSTBWNB/DOW-CE:03/2018 303M 20% 69M 2024-05-16
PSTB-COI-WNBP-02/2018 872M 12% 27M 2024-05-16
SC44-PGoWNB - 2019 340M 22% 119M 2024-05-16
MC/COI-KHR/WNBP-01/2020 361M 34% 66M 2024-05-16