Contractor Analytics

Total Contract Amount (PGK)
11 Billions
15.6% of the Budget
Overall Completion
6%
-2.4% Deviation
Time Exceeded Contracts
4
5% of all contracts
Contracts with Varied Value
74
+5 in the last month
Contracts in Defects Liability Period
51
+6 in the last month
Contracts experiencing late payment
30
+7 in the last month
Contracts given extension of time
48
+2 in the last month
Value of Contract Variation (PGK)
223 Millions
0.9% of the Budget
Payable Amount (PGK)
1 Billions
3.6% of the Budget
Budget Balance (PSK)
20 Billions
84.6% of the Budget
Overall Progress
Corridor-wise Progress
Contract Budget Completion % Paid Amount Expected End Date
CSTB 2930 198M 12% 95M 2024-05-16
CW-14-2016 591M 29% 106M 2024-05-16
50-NBD/DoW-20/01 to 20/06 807M 38% 95M 2024-05-16
DoW AROB SK04/2020 703M 27% 51M 2024-05-16
CW-13-2022 349M 34% 23M 2024-05-16
NBE - INF/PIP - 2021 - 01 138M 23% 50M 2024-05-16
WNBPSTB/DOW-CE:01/2018 139M 11% 65M 2024-05-16
PSTBWNB/DOW-CE:03/2018 488M 38% 77M 2024-05-16
PSTB-COI-WNBP-02/2018 137M 33% 41M 2024-05-16
SC44-PGoWNB - 2019 290M 10% 29M 2024-05-16
MC/COI-KHR/WNBP-01/2020 898M 17% 47M 2024-05-16