Contractor Analytics

Total Contract Amount (PGK)
6 Billions
15.6% of the Budget
Overall Completion
7%
-2.4% Deviation
Time Exceeded Contracts
4
5% of all contracts
Contracts with Varied Value
69
+5 in the last month
Contracts in Defects Liability Period
18
+6 in the last month
Contracts experiencing late payment
21
+7 in the last month
Contracts given extension of time
26
+2 in the last month
Value of Contract Variation (PGK)
165 Millions
0.9% of the Budget
Payable Amount (PGK)
4 Billions
3.6% of the Budget
Budget Balance (PSK)
7 Billions
84.6% of the Budget
Overall Progress
Corridor-wise Progress
Contract Budget Completion % Paid Amount Expected End Date
CSTB 2930 851M 23% 86M 2024-05-16
CW-14-2016 656M 37% 82M 2024-05-16
50-NBD/DoW-20/01 to 20/06 359M 33% 21M 2024-05-16
DoW AROB SK04/2020 505M 33% 115M 2024-05-16
CW-13-2022 889M 20% 105M 2024-05-16
NBE - INF/PIP - 2021 - 01 870M 37% 75M 2024-05-16
WNBPSTB/DOW-CE:01/2018 769M 39% 101M 2024-05-16
PSTBWNB/DOW-CE:03/2018 751M 15% 95M 2024-05-16
PSTB-COI-WNBP-02/2018 286M 28% 21M 2024-05-16
SC44-PGoWNB - 2019 450M 14% 24M 2024-05-16
MC/COI-KHR/WNBP-01/2020 192M 22% 55M 2024-05-16