Contractor Analytics

Total Contract Amount (PGK)
13 Billions
15.6% of the Budget
Overall Completion
4%
-2.4% Deviation
Time Exceeded Contracts
5
5% of all contracts
Contracts with Varied Value
83
+5 in the last month
Contracts in Defects Liability Period
44
+6 in the last month
Contracts experiencing late payment
53
+7 in the last month
Contracts given extension of time
21
+2 in the last month
Value of Contract Variation (PGK)
189 Millions
0.9% of the Budget
Payable Amount (PGK)
4 Billions
3.6% of the Budget
Budget Balance (PSK)
8 Billions
84.6% of the Budget
Overall Progress
Corridor-wise Progress
Contract Budget Completion % Paid Amount Expected End Date
CSTB 2930 222M 37% 85M 2024-05-16
CW-14-2016 481M 36% 73M 2024-05-16
50-NBD/DoW-20/01 to 20/06 521M 26% 64M 2024-05-16
DoW AROB SK04/2020 764M 22% 78M 2024-05-16
CW-13-2022 448M 38% 100M 2024-05-16
NBE - INF/PIP - 2021 - 01 536M 26% 41M 2024-05-16
WNBPSTB/DOW-CE:01/2018 344M 31% 100M 2024-05-16
PSTBWNB/DOW-CE:03/2018 297M 35% 64M 2024-05-16
PSTB-COI-WNBP-02/2018 114M 14% 65M 2024-05-16
SC44-PGoWNB - 2019 845M 25% 30M 2024-05-16
MC/COI-KHR/WNBP-01/2020 784M 19% 37M 2024-05-16