Contractor Analytics

Total Contract Amount (PGK)
14 Billions
15.6% of the Budget
Overall Completion
13%
-2.4% Deviation
Time Exceeded Contracts
5
5% of all contracts
Contracts with Varied Value
92
+5 in the last month
Contracts in Defects Liability Period
17
+6 in the last month
Contracts experiencing late payment
29
+7 in the last month
Contracts given extension of time
17
+2 in the last month
Value of Contract Variation (PGK)
83 Millions
0.9% of the Budget
Payable Amount (PGK)
3 Billions
3.6% of the Budget
Budget Balance (PSK)
7 Billions
84.6% of the Budget
Overall Progress
Corridor-wise Progress
Contract Budget Completion % Paid Amount Expected End Date
CSTB 2930 724M 28% 32M 2024-05-16
CW-14-2016 154M 32% 79M 2024-05-16
50-NBD/DoW-20/01 to 20/06 152M 24% 34M 2024-05-16
DoW AROB SK04/2020 616M 20% 117M 2024-05-16
CW-13-2022 93M 37% 76M 2024-05-16
NBE - INF/PIP - 2021 - 01 325M 11% 100M 2024-05-16
WNBPSTB/DOW-CE:01/2018 102M 10% 77M 2024-05-16
PSTBWNB/DOW-CE:03/2018 745M 21% 102M 2024-05-16
PSTB-COI-WNBP-02/2018 174M 11% 91M 2024-05-16
SC44-PGoWNB - 2019 582M 16% 118M 2024-05-16
MC/COI-KHR/WNBP-01/2020 129M 27% 51M 2024-05-16